This website requires certain cookies to work and uses other cookies to help you have the best experience. By visiting this website, certain cookies have already been set, which you may delete and block. By closing this message or continuing to use our site, you agree to the use of cookies. Visit our updated privacy and cookie policy to learn more.
This Website Uses Cookies By closing this message or continuing to use our site, you agree to our cookie policy. Learn MoreThis website requires certain cookies to work and uses other cookies to help you have the best experience. By visiting this website, certain cookies have already been set, which you may delete and block. By closing this message or continuing to use our site, you agree to the use of cookies. Visit our updated privacy and cookie policy to learn more.
The new insulated hot water system shall replace the existing pipe distribution and shall include an in-line circulator and standby circulator, normally open ATC control valves to the radiant heat food warmers, DOAS heating, and existing dishwasher heating/booster coil.
The HVAC system selection and design intent is based on the processed outlined in ASHRAE Handbook 2020, Chapter 1, “HVAC System Analysis and Selection.”
As a result of the COVID-19 pandemic, a major convention center located in the southern part of the U.S. has put together an IPD team to update the policy and procedure (P&P) manual with “lessons-learned” over the past 18 months.
A finalized system selection shall consider a central plant heating versus decentralized heating plants, and all specialized systems shall include general exhaust, boiler flue exhaust, and boiler plant ventilation.
The system includes a 2,000-ton open cooling tower with six condenser water pumps and four 500-ton centrifugal electric chillers with two condenser water pumps for process chilled water cooling.
The existing central air system with eight terminal reheat coils shall provide space temperature and humidity control to maintain 40%-60% relative humidity within each room while maintaining 68°F in the heating season, 74° in the cooling season, and space pressure maintained at 0.05-inch gage positive pressure.
A complete energy audit of the primary-secondary chilled water system from the central chiller plant to the individual buildings that make up a casino’s 12-building complex.
As a result of the COVID-19 pandemic, a major hospital in the southern U.S. has put together an IPD team to update the facility's policy and procedure (P&P) manual with "lessons-learned." This update includes a section on HVAC.