Why owners are so accepting

The following letters is in response to Rebecca Ellis’ December 2012 “Commissioning” column titled, “When Substantial Com-pletion Is Unsubstantial,” page 19.

March 11, 2013
/ Print / Reprints /
ShareMore
/ Text Size+

I would not recommend changing your position of commissioning as a prerequisite for substantial completion. I can think of several reasons why owners are accepting facilities before they are substantially complete. They are:

  • Cost savings which compromises project management / construction management
  • I have observed real cost pressures on project management / construction management (PM/CM). Owners are more and more resistant to fully funding the management of design and construction, if they fund it at all. Five to 10 years ago, the range of cost for design phase and construction phase PM/CM was in the 3% to 5% range of total project value. Today, that range is more likely to be 2% to 3%. Very frequently, owners are opting to use their property management or facilities group to perform “PM/CM” with their current staff. The quotation marks are included to convey the point that these groups tend to believe they are performing PM/CM when, in fact, they are contributing to the very problem your article discusses.
  • When PM/CM isn’t performed or not performed well, the most typical outcome is that the design takes longer to complete. The other end of weak or poor design management is excessive changes during construction, which also adds time to the construction duration. All of this occurs with a fixed schedule end point which, according to the owner, cannot move.
  • Economic pressures on owners to show a return on investment.
  • This pressure tends to convince owners not to spend the extra dollars on PM/CM.
  • The market pressures to complete a facility, put it into production, get it rented, etc., continue to increase as the interest rates stay low — money in the bank isn’t earning anything. So investment in facilities moves up the priority list to generate return. The quicker a facility is finished, the sooner the payback starts.
  • A fundamental lack of insight on the part of owners about how they are compromising their new facility.
  • Owners just don’t understand how MEP systems function. They are just taken for granted. I wonder if owners think about changing the air filter in their home, whether the septic tank should be pumped, etc. I suspect they don’t.
  • Owners are not interested in details, they just want results. This is unfortunate, but a reality.

 I’m sure there are other reasons. These are the ones that come to mind. I think your position is a valuable “standard of practice” and should be retained.

 

Jim Mallon, CCM, PMP, LEED AP

Parsons

Pasadena, CA

 

Ellis responds:

Thank you so much for your insightful comments. They ring true, are well-articulated, and are much appreciated input from a PM/CM professional.

The connection between poor design phase management and end-of-construction woes is excellent. We’ve been able to see lots of trees in that forest in our project experience but haven’t stepped back far enough to see the direct connection between one and the other.

Also, your comment about owners simply not understanding the process and their building systems is consistent with what I have been hearing from other readers — including owners themselves.

I will definitely explore these ideas in future columns.

You must login or register in order to post a comment.

Multimedia

Videos

Image Galleries

ES Gallery: Snapshots & Systems

Check out highlights from projects featured in our magazine this year!
11/20/14 2:00 pm CDT

Key Issues in Selecting Emergency Back-up Generators

Join us for this webinar on key issues for selecting back-up generators, as well as the related critical components in the power chain of emergency power systems.

Engineered Systems Magazine

ES October 2014 cover

2014 October

Check out the October 2014 issue of Engineered Systems, with features on economizers, pump operations, and much more!

Table Of Contents Subscribe

System Design

Based on your experience and knowledge level, are you currently comfortable designing or maintaining a system incorporating VRF or radiant ceiling panels?
View Results Poll Archive

THE ENGINEERED SYSTEMS STORE

The_Green_Energy_Management
The Green Energy Management Book

Learn from our experts how to evaluate job opportunities, market your services, sell a Walk-through Survey, target areas for an Energy Audit, calculate energy savings, do retrofit work, and win continuing contracts for retrofit work.

More Products

Clear Seas Research

Clear Seas Research ImageWith access to over one million professionals and more than 60 industry-specific publications,Clear Seas Research offers relevant insights from those who know your industry best. Let us customize a market research solution that exceeds your marketing goals.

Tomorrow's Environment Podcast

This series from longtime columnist and chronic forward-thinker Howard McKew covers a lot of ground -- from retrocommissioning to systems training, on toward checklists for drawings and tips for meeting minutes. Click HERE to be taken to the podcast page!

STAY CONNECTED

new Facebook icon Twitter icon YouTube iconLinkedIn icon  Google+