This presents unique design considerations for hvac systems. Recently, Parsons successfully constructed an award-winning D-B Web hosting facility in the Atlanta area for a leading telecommunications client. This project was completed and turned over to the client within five months from the start of preliminary design.
This project required 35,000 sq ft of raised floor server space to be constructed in the first phase of construction. The design had to accommodate a final build capability of 110,000 sq ft of raised floor space.