
Park
Plaza Condominiums, a nine-level mixed-use property in Pittsburgh,
achieved electrifying results after retrofitting more than 120
submeters over a 35-day period.
Located
a few blocks from Pittsburgh’s Carnegie-Mellon University, Park
Plaza Condominiums, a nine-level mixed-use property, is home to more
than 100 resident owners and various commercial offices, including
Park Plaza Condominium Associates, the building owner.
Pressured by rising costs, the property
manager - Arnheim & Neely - was faced with either raising
monthly fees to offset the property’s $20,000 per month electric
bill or finding a way to allocate and bill each owner’s electrical
usage in order to recover a significant percentage of the facility’s
operational overhead. Seeking to work with the owners, some of whom
had been in the building up to 30 years, Park Plaza Condominium
Associates chose the latter option.
Submetering Solution
A&N
estimated that running additional power company metering to each of
the building’s more than 120 units would be five or six times
costlier than simply submetering each apartment, including all
residential units, to isolate each owner’s electrical usage (kWh)
behind the main utility meter.
Submetering
turned out to be the ideal solution for this application and a great
way to avoid the inherent unfairness of traditional ratio-based fees
commonly used in the industry. Based on a simple cost-per-square-foot
formula, ratio-based structures favor high-consumption users by
unfairly saddling low-use consumers with shared costs beyond their
control or ability to manage. Submeters prevent such inequities and
eliminate disputes by providing proof of actual energy usage.
At this point, the electrical contracting
firm, Scalise Industries of Lawrence, PA, was called in. As service
manager of the electrical division, Phil Reiss was given the job of
managing the project, finding a vendor, and supervising the
submetering installation. Based on prior experience with the popular
E-Mon D-Mon submeters, Reiss worked out the details with his local
distributor, Tony Rinehart of Scott Electric, and the local E-Mon
rep, Jack Group. When asked why he specified E-Mon over some other
submetering vendor, Reiss stated that “E-mon has the best equipment
from our experience.”
Once the job got
underway, the team of manufacturer’s rep, distributor, and project
manager functioned like a well-oiled machine. “Scott Electric
didn’t have an order that size in stock,” Reiss explained.
“However, the factory got us all the equipment in a very timely
fashion.”
Installation Challenges
Submetering
the twelve commercial spaces on the ground floor proved less
challenging than metering the residential floors above. “The entire
building had finished drywall ceilings with limited access for
cabling,” said project manager Reiss, who explained that the 200A
split-core current sensors were installed in an existing junction box
in the hallway just outside each apartment.
“We
were able to pull cables from all the current sensors down to the
MMUs. All the new cabling came through the corridors, then down the
electrical riser closet to the basement.” The hinged construction
of the low-voltage (0 to 2V) output split-core current sensors
allowed the electricians to install them non-invasively around the
electrical feeds being monitored, thus eliminating the need to shut
down the load and resulting in a safer, faster install.
In
the basement, an Ethernet cable was run a few feet from the MMUs to
the building’s engineering office where a desktop PC running E-Mon
EnergyTM software is used
to analyze the meter data and output monthly owner billing
statements.
Energy Cost Savings
Begun
March 12, 2008, the entire project took only 35 working days for
Scalise foreman Pat Kelly, who did the layout and most of the
installations, assisted by Mike Petrosky. Since it went operational,
Arnheim & Neely calculates that the system’s $113,000 installed
cost paid for itself in only seven months - based on $16,000 per
month in electrical costs that were recovered as a direct result of
submetering the property. Park Plaza has no need to expand its
existing system right now, but should the owners decide to factor
common-area electrical usage - another $4,000 per month -into the
mix, it would be an easy matter to retrofit additional meters to
recover those costs as well.
“The property
manager is very satisfied with the entire system,” said Reiss,
“especially how the software can collect all the data and produce a
monthly statement to send to the building’s residents.”
For their part, the resident owners ought to
be thrilled as well. Thanks to the property manager’s appreciation
of Park Plaza’s valued residents, a system was installed that
forestalled the necessity of raising monthly maintenance costs by
providing a means to fairly and accurately assess individual
electrical usage. Allocating actual costs to the using parties
allowed these farsighted property owners to “kill two birds with
one stone” by improving the facility bottom line while also
increasing owner satisfaction through more fair and equitable billing
practices.
ES