Biomass - Through the Looking Glass
by Chip Lederer
December 1, 2009
A
window and door manufacturer that used up to 100,000 lb/hr of steam
was informed that its steam source was being eliminated. No problem!
Working with a design firm forged a clear vision: overhauls of its
steam and biomass systems, plus a warm-water recovery plan that took
advantage of (and protected) the local environment. See how the
company’s HVAC emerged renewed and renewable.
Engineers
who offer clients ‘outside the box’ thinking not only solve the
issue of the day but also provide solutions that meet their clients’
needs well into the future.
Such was the case
with a recent engineering project for Andersen Corporation, where
TKDA met the initial need of finding a new source of steam for the
company but also designed a warm-water recovery system that went
beyond the initial scope of the project and met Andersen’s
long-range goals.
The Situation
 |
| Figure
1. A
steam-generating facility for Andersen Corp. features two 40,000
lb/hr wood/gas fired boilers. |
|
Andersen
Corporation (Bayport, MN) is the largest window and door manufacturer
in North America. The company’s campus is located on the St. Croix
River — a national scenic river way that flows into the Mississippi
River. In 2005, Andersen Corporation was
notified that they would need to find a new source of steam for their
facility. They had been generating a portion of their steam in-house
and purchasing additional steam from a nearby thermal facility, which
was changing its offerings and could no longer meet Andersen’s
needs.
With
less than 24 months to have the new system designed, developed, and
installed, the company hoped to find an innovative solution that not
only replaced their old system that included an antiquated wood-fed
boiler system, but also lessened the environmental impact of their
facility on the nearby community while adhering to extensive
regulatory requirements.
TKDA, an engineering,
architecture, and planning firm headquartered in Saint Paul, MN,
offered an innovative solution that went beyond Andersen’s initial
needs and designed a facility that eliminated Andersen’s reliance
on coal-based steam, decreased its landfill waste and emissions, and
enabled the company to control its current and future energy
requirements by using new, state-of-the-art equipment.
The Solution
After
many discussions and a thorough feasibility study, TKDA designed a
$22 million facility that gives Andersen the flexibility to produce
virtually 100% of its required steam and heat from renewable energy.
The project included three distinct parts: a
warm-water recovery system, a steam-generating facility, and a
wood-handling system.
The steam-generating
facility consists of a 15,000-sq-ft building that is sized for the
peak production of 120,000 lb/hr of saturated high pressure steam,
which meets Andersen Corporation’s peak steam requirement of
100,000 lb/hr (or equivalent heat load). This was accomplished by
using two 40,000 lb/hr wood/gas-fired boilers, one gas/oil-fired
40,000-lb/hr back-up boiler and four 100,000 cfm makeup AHUs.
 |
| Figure
2. The
facility also includes a dual-fuel natural gas/low sulfur fuel oil
boiler. |
|
TKDA’s
design incorporated a warm-water recovery system to heat outside air
brought into the facility, thus reducing the wood fuel needed to heat
the building. The system takes warm wastewater from a nearby energy
plant and pulls heat from it for heating fresh air in the three
million sq-ft-facility. Specifically, the
warm-water recovery system pumps 60°F condenser cooling water from a
discharge canal located one-quarter mile away through a reused 10-in.
steam piping system to the makeup AHUs. This water is then
distributed to the four makeup AHUs used to temper the 400,000 cfm of
outside air that is introduced into the manufacturing area.
The outside air is brought into the facility
through wall louvers. The makeup AHUs also have a redundant energy
source of steam and natural gas that can be used if needed. Once the
water passes through the makeup AHUs, it is routed to an outfall and
discharged into the St. Croix River National Scenic Waterway.
 |
| Figure
3. A
warm-water recovery system pumps 60°F condenser discharge water from
a nearby energy plant and pulls heat from it for heating fresh air in
the 3 million-sq-ft facility. |
|
The
warm-water recovery system eliminated Andersen’s need for a fourth
boiler because using the heat from the warm water reduces the steam
load to the point where the third gas/oil dual-fuel boiler operates
as the back-up boiler. After a year and a half of operation, it has
proven to be a real cost benefit as it reduced the steam load by
30,000 lb/hr. It also reduced the amount that flows into the nearby
St. Croix River from the adjacent power plant. The warm-water AHUs
provide the equivalent thermal load of one wood-fired boiler unit.
Installation of four large AHUs offset the need for an additional
boiler through reuse of heat recovered from the condenser water.
These units also reduced fugitive air infiltration by approximately
80%. Special low nitrogen oxide (NOx) burners
were also installed as a backup heat source to the warm water. This
was the first time low NOx burners have been used in this manner
outside of California. The design provides reduced energy consumption
and improved performance. If needed, flue gas may be recirculated to
further reduce nitrogen oxide emissions. Flue gases pass through an
electrostatic precipitator to remove particulate matter emissions.
A third component of the design involved a
system of wood-fired boilers that actually recycle the facility’s
waste products, so the excess wood from manufacturing doors and
windows becomes fuel for the boilers.
 |
| Figure
4. TDKA
met Minnesota Pollution Control Agency emission requirements with a
low-cost electrostatic precipitator at the Andersen Corp.
headquarters. |
|
Specifically,
wood waste from the manufacturing process is run through a hammer
mill, making it into wood ‘flour’ that can be fed into three
boilers through a pneumatic system and metered into the boilers,
which use low NOx burners. The boilers were designed to accept the
wood flour, ensuring complete combustion and minimal ash generation.
(A positive byproduct of the new process — an ash utilization
program for soil enhancement by local crop farmers is being planned
to replace a previous waste landfill program.) Andersen
is one of the first companies in the nation to install new boilers
that meet the Industrial Boiler National Emissions Standards for
Hazardous Air Pollutants. The new facility reduces permitted emission
limits of criteria pollutants by 53%. Building a new plant on site
also enabled Andersen to decommission all six existing wood or fuel
oil-fired boilers.
The Result
The
new steam-generating facility, which was fully functional in May of
2007, adheres to Andersen’s environmental performance guidelines
for both manufacturing products and process. In addition, it requires
less energy and offers superior performance.
The
facility was constructed by the design/build team assembled by TKDA
that included Pioneer Power, Siegfried Construction, and Hunt
Electric. TKDA has earned several awards for this project including a
national honor from the American Council of Engineering Companies.
 |
| Figure
5. TDKA
designed a heat recovery and steam facility for Andersen Corp. that
reduces the steam load by 30,000 lb/hr and also reduces the amount of
water that flows into the nearby St. Croix River. |
|
While
finding and developing new technologies that work is important, it is
paramount that engineering firms look for ways to bring these new
ideas together for the good of the client. For
instance, starting from the ground up, the team minimized regulatory
interaction on the site’s flood plain and scenic St. Croix River by
utilizing the footprint of an existing storage building. In addition,
existing steam pipeline was used for water transfer, vs. being
replaced, which eliminated the need for installation of a new water
transfer pipe. As more and more companies
seek to reduce their consumption of natural resources due to federal
mandates, engineering firms need to offer creative solutions. TKDA
recently dedicated a team to focus solely on providing energy saving
designs and plans that provide energy efficient alternatives for
facility heating, power and cooling for a variety of building types
and infrastructure. TKDA’s engineers
successfully brought an innovative solution to Andersen by designing
a system that produces efficient, renewable energy while allowing
Andersen’s manufacturing operations to remain environmentally
sensitive to the nearby St. Croix River. ES
|