Commissioning: On-Board Equipment Controls Integration
by Rebecca Thatcher Ellis, P.E.
February 1, 2010
Design
engineers need to step up how their specs sort out sequencing
details.
Last
month, this column addressed the timing of control system design at a
very high level. This month, I would like to drill down a bit and
discuss an aspect of control system design which has proven
particularly challenging for commissioning — the documentation and
integration of on-board equipment controllers.
More
and more equipment is coming with its own factory-installed and
programmed controllers. This can be true for boilers, chillers,
rooftop units, makeup air units, heat pumps, etc. How these on-board
controllers are integrated — or not — into the overall HVAC
systems can demand an inordinate amount of commissioning
attention.
One of the fundamental issues is
the difficulty in obtaining detailed sequences of operations for the
controllers from the manufacturer. That level of detail is not
typically provided as part of a standard equipment submittal package.
Once the documentation is provided as part of a re-submittal, it
invariably comes in a generic format with multiple options defined.
This requires at least one more re-submittal where the manufacturer
identifies which options will be set-up/programmed for the current
project.
Unfortunately, this level of review
and re-review prior to ordering the equipment is not practical given
most construction schedules, and equipment will be ordered with an
understanding that the control system information will be ironed out
later.
Later Can’t Wait
“Later”
can easily be put off — regardless of commissioning efforts to
expedite — until equipment startup when the start-up technician
performs the actual setup/programming of the on-board controllers.
This will be done based on the technician’s past experience, best
intentions, and often-limited understanding of how the equipment fits
into the bigger picture of the HVAC system.
After
startup, the pursuit of documentation could be frantic as the overall
system functional performance testing approaches and the
commissioning professional has no customized controller information
with which to develop final test procedures. Having the start-up
technician write down exactly how a particular controller was
programmed would be best but, again, proves to be a time-consuming
challenge with mixed results. Having the commissioning professional
witness every startup procedure and document all of the settings is
another option, but is not typically part of a commissioning scope of
services.
It is not unusual to begin
functional testing without the project-customized equipment control
sequences due to project schedule pressures. In this case, functional
testing is the process by which the commissioning professional learns
how the equipment works, not “testing” at all, but
“investigation.” This takes more time in the field than
performing a focused test of pre-defined sequences of operation. To
be most effective, this also requires the participation of the
start-up technician (or someone else fluent in the on-board
controller and its programming) to demonstrate controller performance
and interpret the often-cryptic user interface.
That’s
the sad story of the construction phase. Why did I start there?
Because we see almost no attempt at specifying, documenting, or
coordinating on-board equipment controllers in the design phase.
Too Many or Not Enough
In
the worst of cases, we see design specifications which call for
on-board controllers in the individual equipment specification
sections plus control points and sequences of operation for the same
equipment in the DDC system specification section. At a minimum, I
believe the design engineer is responsible for coordinating how each
component of the HVAC system is to be controlled and ensuring there
is neither duplication nor missing details.
Even
when the controls responsibility is clearly defined between DDC and
on-board controllers, there is almost always a scarcity of
information regarding the on-board controller sequences of operation.
Regardless of who is responsible for providing the control components
and logic, I believe the design engineer is responsible for defining
the expected operation. For on-board controllers, this means the
effort spent understanding the capabilities of the manufacturer’s
hardware and software should be expended in the design phase so that
the engineer can specify which options are to be selected for the
project.
If there is to be any interface
between the on-board controllers and the DDC system, this also needs
to be unambiguously defined in the design specification. Simply
stating that the equipment controller shall “integrate with the DDC
system” is not specific enough. The design needs to define which
points are to be monitored by the DDC system, which alarms are to be
sounded at the DDC system; what information the on-board controller
should accept from the DDC system (setpoints, schedules, etc.), which
on-board controller points should be displayed on the DDC system
graphics, etc.
If we can all agree that the
building owner is entitled to obtaining accurate, customized, and
timely documentation of all aspects of the control system —
including the details of the on-board equipment controllers — at
the end of construction, I propose that it will be most efficient and
effective to start that documentation in the design phase. Even if we
need to pay design engineers more to do the communication and
coordination with the equipment manufacturers, it is much better to
have a clear set of contract documents than to try to accomplish all
of the coordination and review during the construction and startup
phases. ES
|