A new water treatment law nudges a manufacturer to savings
March 1, 2010
 |
| A
chemical-free water treatment plan has reduced Playtex Products’
discharge water by 60% and has resulted in a 43% reduction in water
use, saving the company money. |
|
In
2007, Delaware’s Kent County passed legislation requiring that
users of cooling towers in the county transition from chemically
based to chemical-free water treatment on their cooling systems. The
reason behind this legislation was that biocide residuals in the
discharge (blow-down) water going into the sewer from these systems
made it extremely difficult and time-consuming to treat the water for
any beneficiary purposes.
Upon reviewing this
new regulation, Ismail (“Smiley”) El-Abd, P.E., a vice president
with the G.F. Morin Company in Laurel, MD, advised one of his
long-term clients, Wayne Rossi, director of engineering, in the
Playtex Products plant in Dover, DE, that he had a solution for this
mandate.
Installing the Dolphin System™
water treatment would fulfill the legislative requirements of Kent
County and provide economic benefits as well. Having a solid working
relationship and history of trust with Smiley, Wayne agreed to look
into the possibility of changing from chemical treatment of his
cooling towers and boilers to the chemical-free alternative. However,
there was one major caveat: the economics of such a proposal had to
be justified.
Planning to Achieve Goals
The
initial step in planning for the potential installation of the
Dolphin System on four cooling towers and two steam boilers was to
obtain and analyze the quality of the water coming into these cooling
and heating operations. Smiley and personnel from Clearwater Systems
Corporation, manufacturer of the Dolphin System, Mark Winter,
director of engineering, and Jamie Downie, senior manager of
technical support, looked at the conductivity setpoints for the
cooling towers and boilers under chemical treatment. They agreed that
the chemical-free alternative would produce savings in purchasing the
water, using less water during operations through higher cycles of
concentration (COC), and in reducing the water volume going to
sewer.
Based on the amount of chemicals being
used, conservative estimates were that approximately 30% in water
savings could be achieved under the Dolphin System. These preliminary
findings interested Wayne Rossi and his team members at Playtex —
Joe Konrad, Craig Weidner, and Lawrence Haldeman — to move forward
with the concept.
Although
the Kent County legislation on banning cooling tower discharge water
into sewers was being held up in litigation at the time, there were
other stimuli to make this transition. Some of Playtex’s
high-profile clients were implementing green policies on their
business operations and were asking their product and service vendors
what they were doing to lessen the environmental footprint of their
own operations. By installing the Dolphin System, Playtex would have
a compelling story to tell how the plant fulfilled such goals.
Results
The
project called for a Dolphin System installation on a cooling tower
located outside the building, three cooling tower installations
inside the building, and two steam boiler installations inside the
building.
The outside cooling tower, used for
air conditioning, comprises approximately 1,200 tons of cooling.
Following the Dolphin System installation, the cooling system began
to “de-scale,” with scale coming off from the fill and settling
in the cold water basin of the cooling tower. The re-circulating
water was crystal clear, the system was operating at higher COCs than
under chemical treatment, and total bacteria counts (TBC) were in the
hundreds, far better than what is typically determined as “excellent
water treatment” by the Cooling Technology
Institute.
Furthermore, efficient heat
transfer, as indicated by the approach temperature, was being
maintained. Under chemical treatment, the total water use was
estimated at 16,200 million gallons per year (mgpy), while under
Dolphin System treatment, the total water use is 11,340 mgpy,
resulting in a 30% reduction in total water use. This reduction is a
direct result of increased COCs, resulting in less blow-down or
discharge water. Under chemical treatment, water discharge was
calculated as 8,100 mpgy; the water discharge is 3,240 mgpy under
Dolphin System control, resulting in a 60% water discharge reduction.
The inside cooling towers, specifically tower
3, 4, and 6 are used to maintain humidity control so the cellulose
fiber used to make Playtex products can be processed. At first, the
TBC results from this tower were considerably higher than the results
from the outside tower, due to an inordinate amount of cellulose dust
in the surrounding air. The joint decision among G.F. Morin,
Clearwater, and Playtex personnel was to replace the cooling tower
fill pack and drift eliminators, thereby bringing the overall cooling
system back to its initial condition. An improved filtration system
was also installed to minimize cellulose fiber concentration.
When these adjustments were made, TBC counts
noticeably decreased. Within two to three weeks, TBCs were under
1,000 colony forming unit (cfu)/ml. Under chemical treatment, the
total water use for this tower was calculated as 4,990 mgpy, as
compared to Dolphin System water use at 2,851 mgpy, resulting in a
43% reduction in water use (a direct result of increased COC
resulting in less blowdown water). Under chemical treatment water
discharge was calculated at 3,564 mgpy. Under Dolphin System
control, water discharge is 1,426 mgpy, equating to a 60% reduction
in water discharged to sewer.
Later on, when
cooling towers 3 and 4 were initialized under Dolphin System
operation, neither the fill pack nor the drift eliminators were
changed. Still, the TBC levels were reduced to less than 2,000
cfu/ml, then later averaging less than 1,000 cfu/ml.
The
two boilers operate on alternative annual use (one boiler in
operation for a year, then shut down as the other one goes into
operation, etc.). After a season of operation under Dolphin System
control, the boiler in use was opened and found to be in optimal
condition: no scale, no corrosion. These operational results
correspond directly to energy savings through maintaining efficient
heat transfer properties.
The Playtex team was
very committed to making the transition from chemical treatment to
chemical-free treatment work. Investing in the Dolphin System and in
new filtration was well worth the investment. Payback has already
been achieved, and continued cost savings will make its mark for
years to come, all with creating a safer and healthier environment
for Playtex employees and their community. ES
|