Alumni Center adds to modern feel with frictionless chiller
February 1, 2009
 |
| A
new frictionless chiller, VFDs, and energy management system has
saved the McNamara Alumni Center at the University of Minnesota
169,130 kWh during its first season of operation. |
|
The
McNamara Alumni Center at the University of Minnesota is designed as
a campus showplace. With its granite-covered geodesic-shaped exterior
and impressive 85-ft atrium, the 231,000-sq-ft structure is a
combined visitor and conference center as well as office building for
University staff.
The building is owned by
the University Gateway Corporation, a non-profit corporation
comprising representatives from the University of Minnesota Alumni
Association, the University of Minnesota Foundation, and the
Minnesota Medical Foundation.
Because of its many functions, the McNamara Center is open
during day and evening hours and on weekends. Despite its
ultra-modern architecture, the building relied on a single 550-ton
chiller for cooling during its first six years of operation. That’s
because the mechanical room was built for the single chiller only —
leaving little room for chiller failures. An ultra-modern HVAC system
had to wait until chiller technology was developed to the point where
smaller machines with adequate capacity would fit in the
room.
When frictionless chiller technology —
with its small footprint — was introduced, Jon McCombs, Alumni
Center operations manager for NorthMarq Corporate Solutions, the
property management firm, recognized the opportunity to add
redundancy to the HVAC system. However, early models were too small
for the load requirements, and there wasn’t enough room to add
multiple units. “When McQuay introduced the 300-ton frictionless
chiller, it gave us both the size and small footprint we needed to
redesign the HVAC system,” said McCombs. “In addition to
redundancy, our goal was to reduce energy and provide significant
life cycle cost savings to the building’s original chiller
plant.”
The end result is that the 300-ton
McQuay chiller runs about two-thirds of the time, with the 550-ton
chiller providing redundancy and carrying larger loads. The new HVAC
system reduced energy costs by 10 percent during the first year both
chillers were in operation.
Meeting requirements for redundancy
When
magnetic-bearing compressor technology did arrive, McCombs saw it as
the solution to issues not only of redundancy, but also of energy
savings and mechanical room restrictions. McCombs worked with Lindell
Engineering (Minneapolis) and completed first designs around a
210-ton stainless steel plate heat exchange chiller. This design
saved energy but presented maintenance limitations. Cleaning the
condenser required completely taking it apart, and the stainless
steel plate added to the unit’s weight.
The
mechanical contractor on the project, Albers Mechanical, knew of
McCombs’ concerns and suggested he consider McQuay’s frictionless
chiller, which had just been introduced to the market. “This new
chiller technology appeared to give us the compact footprint and part
load performance — with the added benefit of extremely quiet
operation — that we needed,” said McCombs. Another benefit of the
new frictionless centrifugal chiller is that the shell and tube
design is easier to service than the steel plate heat exchanger. The
equipment supplier, Schwab Volhaber Lubratt (St. Paul, MN), helped
spec the new chiller.
Redesigning to save energy
McCombs’
first goal was to improve energy efficiencies in the spring and fall.
Because about half of the McNamara Center remains open in the
evenings and on weekends for special events, McCombs thought the best
energy savings would come from shifting after-hours and spring/fall
responsibility to the new McQuay frictionless chiller. That would
leave the 550-ton chiller for those hours when it was really
needed.
During the design phase, McCombs and
his team also installed VFDs on both the evaporator (chilled water)
pump and condenser water pump (cooling water tower) piping systems
and added digital flow meters to monitor both piping systems’ gpm.
As a result, they were able to regulate flow and regain some flow
loss due to triple-duty valves installed in the original design.
Removing the triple-duty valve from the equation increased flows to
both the chilled water and condenser loops and further reduced energy
lost to the triple-duty valve.
Automatic transfer switch simplifies power-sharing
To
take advantage of the existing electrical supply, McCombs installed
an equipment automatic transfer switch. The switch transfers power
between chillers, depending on which one is running (they don’t
operate at the same time). New VFDs adjust flow rates as required for
each chiller’s design, which is a big help in simplifying the
operation and saving energy. He also installed an amp meter to
monitor both chillers’ electrical use from the same source. By
selecting the chiller that matches the load, McCombs reduces energy
and increases the life cycle of the original chiller. In addition,
the new system gives him redundancy to around 85° outdoor air
temperature.
Another benefit is the ability to
integrate with the new Johnson Controls Metasys® energy management
system. The chiller communicates control and monitoring information
to the Metasys system using BACnet®.
Putting it all together
During
its first season of operation, the McQuay chiller faced a higher
number of degree days for cooling, compared to the average of the
past three years. Factor in the new VFDs and lower gpm in the AHUs,
and the new system has saved about 169,139 kWh. At the current local
electricity rate (about 7 cents/kWh), that’s 10% less in energy
costs compared to operating one non-redundant chiller system. The
McQuay chiller is in use about 65% of the time — whenever the part
load performance gives the most energy benefit. That can be as low as
0.33 kW/ton IPLV.
Seasonal runtime hours on
the original 550-ton chiller have been reduced by approximately 1,800
hours. Total chiller runtime hours are approximately 3,000 hrs/yr.
The larger chiller operates for just over
one-third of the season. “We’ve learned that, as the frictionless
chiller gets close to full load, we achieve additional cost savings
by running the larger machine at partial load,” said
McCombs.
Working in tandem, the two chillers
give the McNamara Center the redundancy and reliability it needs. As
a result, McCombs can ensure University staff and guests that they
can rely on the building’s cooling effects even on the hottest
days, while he’s ensured of saving valuable kWh. ES
|